INSTRUCTIONS
FOR LAYING FERRCON DESIGNER TILES
|
1 |
Prepare base mortar with cement and sand in the ratio
of 1: 4. |
2 |
The total mortar thickness should not be more than 25
mm. |
3 |
Set the levels for the floor i.e., dead level or slope
to be specified |
4 |
Prepare
cement slurry with cement and water to form a thick paste
and spread it on the leveled mortar. |
5 |
Wet the rear side of the tile with water.(Complete immersion
of the tile is not necessary) |
6 |
If
tiles are square or rectangular in shape, set the right
angles for the area and place the first tile along the
right angle line on base mortar. Tap gently with a rubber
mallet to get perfect level. |
7 |
After laying, immediately clean the surface of the tiles
with clean, wet sponge Ensure that the base mortar cement
which squeezes through joints does not settle on the tile |
8 |
Let the joint fill naturally. Do not use joint filler. |
9 |
Do not use the area for 48 hours. |
10 |
Wash the surface will soap water or mild detergent to
get a clean surface. |
1 |
1 |
DESIRED
CONDITIIONS FOR LAYING OF FERROCON
DESIGNER PAVERS |
1 |
Set the floor level with wet sand for 50 mm thickness
and compact by using Vibrating plate Compacter |
2 |
Keep the sand with moisture content. Do not use sand which
is 100%dry. |
3 |
Do not spread the sand for longer areas, as it will dry
out and reduce the performance. Use sand of 50mm spreaded
properly. |
4 |
Lay the interlocking paver in compacted sand floor and
tap gently with a rubber mallet to get perfect joints. |
5 |
Spread river sand on the laid area to fill the joint gaps
and run the Vibrating Plate Compactor to get the perfect
level. |
6 |
Construct retention wall all-around the laid areas to
attest the movement of paver blocks. |
7 |
It is recommended to provide the slope of 3 inches on
the wider side and 2 inches on the linear side for every
laying area. |
11 |
11 |
THE
FOLLOWING HAVE TO BE COMPLETED PRIOR TO COMMENCING LAYING
OF FERROCON TILES; |
1 |
Final painting of ceiling in rooms |
2 |
Wiring and fixing of all electrical components to be completed. |
3 |
Plumbing work to be completed. |
4 |
Fixing of grills for windows. |
5 |
Fixing and polishing of windows /window frames/door frames
and doors to be completed |
6 |
If mosaic/Marbles/any other stone which needs machining
or polishing is being done in any part of the floor, it
is necessary that this work is completed before commencing
the laying of Ferrocon Tiles. |
1 |
|